Bancroft Hall Renovation

January 17, 2014

Through the next few weeks, Bancroft is scheduled to undergo continuous demolition of its interior between the hours of 7:00 am and 3:00 pm, Monday through Friday.  Due to the nature of the work, there will be associated construction noise and potential dust as a result.  The contractor will be disposing of all construction debris utilizing a comprehensive dust mitigation procedure and process.  All debris and garbage disposal will be on 121st street with continuous site supervision during the project.  

We apologize for the inconvenience during this time, and appreciate your full cooperation.

DEMOLITION                                     12/13 - 04/14

CONSTRUCTION

8TH FLOOR                                           6/14 - 8/14

7TH FLOOR                                           2/14 - 4/14

6TH FLOOR                                           3/14 - 5/14

5TH FLOOR                                           4/14 - 6/14     

4TH FLOOR                                           5/14 - 7/14

3RD FLOOR                                           6/14 - 8/14

2ND FLOOR                                           7/14 - 9/14

1ST FLOOR                                           8/14 - 10/14

CELLAR                                                5/14 - 9/14

ELECTRICAL SWITCHGEAR                  7/14 - 10/14

STREET CONNECTIONS WORK            4/14 - 6/14

COMMISSIONING                                  9/14 - 11/14

TURNOVER                                           12/14